Thursday, 4 September 2025

Aminex: Rig Strategy and Options for the Ntorya Drilling Campaign

From regional workhorses to ARA’s own fleet, what rigs could deliver the next phase at Ntorya — and when might they spud?


1. Why the Rig Choice Matters

With pipeline construction equipment due to mobilise this month and the Ntorya gas field poised for its next stage of development, investors are rightly asking: when will the next well be drilled, and which rig will do the job?

The answer lies in the rig tender now under way. PURA has approved the strategy, ARA has invited expressions of interest, and a range of options are now on the table.


2. Regional Candidates

Several rigs already in East and Southern Africa meet the technical requirements for CH-1 and the NT-1 workover (~1,000–1,500 HP, ~3–4 km depth capability):

  • Exalo Rig 202 – currently warm-stacked with Invictus Energy in Zimbabwe. Its two-year extension (signed Dec 2023) suggests availability by late 2025, aligning neatly with Ntorya’s timeline.

  • PR Marriott rigs (Kenya) – long track record with Tullow and active in East Africa. A credible bidder with mobilisation experience across the region.

  • Nabors rigs (Uganda) – working with Total and CNOOC on Tilenga/Kingfisher, these are world-class units that may rotate out as Ugandan projects mature.

  • Chinese rigs – subsidiaries of Sinopec and CNPC often respond to tenders in the region; they can field suitable units if scheduled availability matches

It’s also possible that a Chinese drilling rig could ultimately be selected. With CPPE and CPTDC already trusted to deliver the pipeline, and China’s wider history of energy infrastructure in Tanzania, investors may wonder if this confidence extends to drilling services too. While the pipeline award does not automatically link to a drilling contract — these are separate scopes of work — the idea of a CNPC or Sinopec drilling unit entering the tender is credible. If it happened, it would underline Tanzania’s comfort with Chinese delivery capacity, while still leaving room for strong competition from Exalo, PR Marriott, Nabors, and others.

3. The ARA Oman Option

ARA Petroleum also operates a fleet of rigs in Oman. In May 2025 they were running three concurrent rigs in Block 44. If Omani operations wind down, ARA could redeploy one of their rigs to Tanzania.

  • Pros: Full operator control, proven rigs, known crews.

  • Cons: Requires demobilisation, shipping to Mtwara, and land transport inland — at least 3+ months lead time.

While speculative, this option demonstrates ARA’s flexibility if regional rigs cannot be secured in time.


4. Timing — December or Early 2026?

  • December 2025: Possible if a regional rig (e.g., Exalo or Marriott) is freed quickly and mobilisation is fast-tracked.

  • January–February 2026: More realistic if tendering, contracting, and mobilisation take their usual course.

  • Alignment with pipeline: Either way, spudding before or during the early pipeline construction phase ensures CH-1 and NT-1 can contribute volumes once first gas flows in mid-2026.


5. Why Investors Should Be Confident

  • Multiple credible rig pools exist within East and Southern Africa.

  • ARA has its own fleet as a fall-back option, underscoring their commitment.

  • Timelines align with pipeline completion in July 2026 — ensuring gas can move to market.


📌 Closing Line:
“The next well at Ntorya is not a question of if, but when. With regional rigs available, ARA’s Omani fleet as a fall-back, and Tanzania’s regulators moving the process forward, the spud window is now clearly in sight — whether as early as December 2025 or into early 2026.”

Thursday, 28 August 2025

Aminex Update: Pipeline Procurement Underway and Rig Tender Process Accelerates

Following yesterday’s RNS, new disclosures confirm Expressions of Interest for rig services have already been issued — ahead of schedule.


Yesterday’s RNS: Two Key Milestones

On 27th August, Aminex released an RNS confirming significant operational progress at Ntorya:

  • Pipeline:

    • Contractors have begun procurement of pipe and equipment for the 35 km Ntorya–Madimba pipeline.

    • Mobilisation of construction equipment is scheduled for September 2025.

    • Groundwork and pipelaying are due to start in January 2026, with completion by July 2026.

  • Rig Tender:

    • The Petroleum Upstream Regulatory Authority (PURA) has approved the tender strategy for a drilling rig.

    • This approval enables drilling of Chikumbi-1 (CH-1) and a workover of Ntorya-1 (NT-1).

    • The RNS stated that Expressions of Interest (EOIs) from service contractors would be requested next week.

  • Condensate Discussions:

    • TPDC, APT, and Aminex also discussed the processing and storage of condensate, highlighting an additional revenue stream beyond gas sales.


Today’s Update: Ahead of Schedule

Less than 24 hours later, it has been confirmed via today’s release on X (formerly Twitter) that the Expressions of Interest have already been issued, a full week earlier than suggested in the RNS.

This over-performance signals:

  • Strong operator momentum from APT.

  • A clear alignment with Tanzanian regulators and stakeholders.

  • A demonstration that the project is moving faster than timelines originally set out.


Why This Matters for Investors

The combination of pipeline procurement, firm groundwork dates, and now the early launch of the rig tender process creates visible momentum on all fronts:

  • De-risked schedule: Procurement and mobilisation show the pipeline is firmly on track.

  • Accelerated rig contracting: The early release of EOIs means CH-1 and NT-1 are moving closer to execution.

  • Additional upside: Condensate monetisation discussions could provide another layer of value.

This update underscores the Government of Tanzania’s and APT’s commitment to delivering Ntorya gas to the Madimba plant on time — and potentially even ahead of schedule.


Closing Thought

Investors have long waited to see Ntorya move from planning into visible execution. With procurement underway, mobilisation imminent, and the rig tender already advancing faster than expected, that moment has arrived.

The project is not just progressing — it is gathering pace.


Wednesday, 27 August 2025

Aminex RNS: Ntorya Operations Update Confirms Pipeline and Rig Milestones

Procurement for the Ntorya–Madimba pipeline begins, groundwork scheduled for January, while PURA approves the rig tender strategy.


Key Highlights from Today’s RNS

  • Pipeline Progress:

    • Contractors have begun procurement of pipe and equipment for the 35 km pipeline linking Ntorya to the Madimba gas processing plant.

    • Mobilisation of construction equipment will begin in September 2025.

    • Groundwork and pipelaying are scheduled to commence in January 2026, with completion targeted by July 2026.

  • Condensate Value Addition:

    • Discussions are under way regarding the processing and storage of condensate volumes from Ntorya — an additional revenue stream beyond gas sales.

  • Rig Tender Milestone:

    • The Petroleum Upstream Regulatory Authority (PURA) has approved the tender strategy for contracting a drilling rig.

    • The rig will be used to drill Chikumbi-1 (CH-1) and perform a workover on Ntorya-1 (NT-1).

    • Operator APT will request expressions of interest from service contractors next week.


Why This Matters for Investors

This RNS confirms that multiple strands of Ntorya’s development are advancing in parallel:

  • Pipeline: With procurement already under way and a firm mobilisation schedule, the long-discussed link to Madimba has moved from planning to delivery. A clear timeline to completion by July 2026 provides investors with visibility.

  • Rig Tender: PURA’s approval is a regulatory green light that allows the operator to advance into contractor engagement. The drilling of CH-1 and the NT-1 workover will expand production capacity beyond NT-2, underpinning volumes for the GSA.

  • Condensate: Monetisation of condensate offers upside beyond gas sales, increasing the value of the project.

Together, these steps strengthen confidence that Ntorya is firmly on its way to first gas, with strong backing from TPDC, PURA, and APT.


Aminex Management Comment

Charles Santos, Executive Chairman, highlighted:

“Our discussions with the TPDC and the operator have been extremely fruitful, and we are delighted that activity on the Pipeline is proceeding as planned… PURA has approved the tender strategy, allowing APT to begin the tender process. These developments demonstrate again the Government of Tanzania’s strong commitment to this project.”


Investor Takeaway

This update provides:

  • Visible progress on the pipeline, with equipment procurement already started.

  • Firm dates for mobilisation (Sept 2025), groundwork (Jan 2026), and completion (July 2026).

  • Regulatory approval clearing the way for the rig tender and the next phase of drilling.

  • Condensate upside adding to the project’s revenue profile.

For shareholders, this RNS delivers the clearest evidence yet that Ntorya’s development is advancing on multiple fronts, backed by Tanzania’s institutions and operator commitment.

Tuesday, 26 August 2025

Aminex Ara Breaking Ground: Ntorya Moves Closer to First Gas

Visible steps are aligning as infrastructure, wells, and regulatory milestones converge toward production.


A Project Now in Motion

The Ntorya development in southern Tanzania is advancing step by step toward its goal of delivering gas into the national grid via the Madimba pipeline. With approvals secured, funding confirmed, and procurement of facilities under way, the project is steadily progressing along its critical path.

Investors are understandably keen to see “hard evidence” — rigs mobilising, welders on the pipeline, or CPF construction above ground. Those milestones are coming, but there is already much happening that gives confidence in the journey ahead.


Upcoming Milestones: The Roadmap Ahead

1. EPC Contract Awarded

The Engineering, Procurement, and Construction (EPC) contract for the 35 km pipeline has been officially awarded to China Petroleum Pipeline and China Petroleum Technology & Development Corporation. This ensures the pipeline’s delivery is now in the hands of experienced international contractors.

2. Pipeline Fully Funded

The pipeline construction is being fully financed by TPDC, the national petroleum corporation. This reduces financial risk for the operators and demonstrates the Tanzanian government’s strong commitment to bringing Ntorya gas to market.

3. NT-2 Extended Well Test & CPF Integration

NT-2 has been identified as the first producing well. An extended well test will confirm reservoir behaviour and fine-tune the CPF’s design specifications. Importantly, this does not delay CPF construction — procurement and enabling works can proceed in parallel, with the test results helping optimise the final equipment setup.

4. PURA Approval for Rig Tender

The regulator, PURA, is reviewing rig tender plans. Approval of this plan is a milestone in itself, as it enables the operator to issue the formal rig tender.

5. Rig Award and Mobilisation

Once the tender is awarded, a drilling rig will be mobilised. Its first task: drill CH-1 (Chikumbi-1). The same rig will then conduct a workover of NT-1. This is a crucial step in adding redundancy and ensuring multiple wells can feed into the CPF and pipeline.

6. CPF Civil Works and Site Preparation

The approved US$41 million budget includes the CPF, flowlines, manifolds, and fiscal meters. While there has been no formal announcement of CPF mobilisation, satellite imagery in the wider Ntorya area shows ground activity that could indicate early site preparation. This should be regarded as an educated observation, not official confirmation.

Such early groundwork is entirely consistent with the development sequence — clearing land, preparing foundations, and creating storage areas typically begin before heavy equipment arrives, ensuring a smooth transition into construction.

7. First Pipeline Welds

The first welds on the pipeline right-of-way will provide unmistakable, visible proof of progress. This is one of the clearest signals investors can look for as the project enters the physical build stage.

8. First Gas Flow

All of these steps lead to the same target: the delivery of 40 MMscf per day under the Gas Sales Agreement in the first contract year, with capacity to grow further.


Investor Takeaway

MilestoneWhat It Demonstrates
EPC awardedContractors in place, work authorised
Pipeline funding by TPDCFull state backing, no financial burden on operator
NT-2 extended testOptimises CPF design, not a blocker
PURA approval for rig tenderRegulatory progress, green light to issue tender
Rig award & mobilisationVisible drilling and well activity
CPF enabling worksSite preparation under way, consistent with plan
First pipeline weldsPhysical build begins in earnest
First gasContracted supply of 40 MMscf/d delivered

Conclusion

Ntorya is progressing through a clear sequence of milestones. Some are less visible than others, but each is a step toward first gas. With the pipeline EPC awarded, funding secured, and wells prepared for development, the project is firmly moving forward.

The next stages — rig mobilisation, CPF civil works, and the first pipeline weld — will provide the visual proof that investors are waiting for. From there, Ntorya transitions rapidly from preparation to production, with 40 MMscf/d contracted under the GSA and a scalable pathway for growth.

Thursday, 21 August 2025

Ntorya’s Central Processing Facility: What It Is and Why It Matters

Practical steps from wellhead to Madimba — what could happen next

When people think of Ntorya and Aminex, they picture wells and a pipeline. The Central Processing Facility (CPF) is the part in the middle that makes everything work. It’s where raw gas from the wells is prepared so it can safely and reliably enter the line to Madimba.

What a CPF does

At a high level, a CPF separates, conditions and compresses the gas:

  • separates water and liquids,

  • dries/conditions gas to pipeline specs,

  • compresses it so it can flow to Madimba.


How it connects to the wells

Each producing well (e.g., NT-1, NT-2, and CH-1) would be linked to the CPF by flowlines. The CPF combines these streams into a single, spec-gas export to the main pipeline. Capacity can be phased so more wells can be added over time.

Where it could be located

Public information points to a location within the wider Nanguruwe/Ntorya ward area so that flowlines are short and road access is sensible. The exact plot is typically confirmed through regulatory steps and company notices; until then, it’s reasonable to assume siting close to the existing well cluster and on a clean line of route toward Madimba.

About testing and why it matters

A mobile test on NT-2 has been discussed to help fine-tune the processing set-up (for example, dehydration and compression requirements). Final equipment specification would normally reflect those test results. In parallel, enabling works at the CPF site (groundworks, civils, fencing, early foundations) can progress ahead of final kit selection, with long-lead equipment orders typically following once test data and approvals are in hand.

Schedule at a glance (indicative)

Subject to approvals and site conditions:

  • Site preparation could proceed first (weeks to a few months).

  • Equipment procurement and installation would typically follow confirmatory testing/approvals.

  • Commissioning would then align with pipeline readiness so first gas can move without delay.

Team and logistics (typical ranges)

Based on similar onshore projects, peak on-site teams can be around 100–200 people, spanning civil, mechanical, E&I and commissioning, with local support for catering, logistics and security. Actual numbers vary with phasing and contractor strategy.

Budget context

Company guidance indicates the approved upstream facilities budget for this phase is intended to cover the CPF plus associated tie-ins, flowlines, manifolds and metering. Exact allocations are usually confirmed in subsequent updates and may be adjusted as testing and procurement progress.

Could start-up be modular?

Yes. A CPF can be delivered in modular packages (skid-mounted separation, dehydration and compression). This approach could enable phased start-up at lower initial rates while full capacity is built out, subject to approvals and commercial agreements.


Bottom line for investors
The CPF is the critical enabler between wells and pipeline. Enabling works may proceed while test results and approvals are finalised, and a modular, phased approach could support an earlier start if required. As company updates arrive (testing schedules, procurement awards, and first-weld milestones), they should help de-risk the timeline and confirm the path to first gas.

This article reflects current understanding and may evolve as formal notices and approvals are published.

Monday, 11 August 2025

Tanzania’s Energy Infrastructure Surge Sets the Stage for Explosive Gas Demand

EWURA’s 109-permit wave, CNG expansion, and major industrial projects point to a multi-year growth engine for Ntorya gas.

Tanzania’s downstream energy build-out is gathering serious momentum. The Energy and Water Utilities Regulatory Authority’s (EWURA) latest Batch 244 public notice lists 109 mid- and downstream petroleum permit applications, covering:

  • Kibali cha Ujenzi wa Kituo cha Mafuta – construction permits for fuel stations

  • Leseni ya Kituo cha Mafuta – licences to operate fuel stations

  • Leseni ya Usambazaji wa Gesi ya Kupikia – explicit LPG distribution licences

  • Other infrastructure-related activities

While the notice does not explicitly label these stations as CNG, the timing, policy direction, and presence of known energy brands such as Puma Energy suggest that many could be CNG-capable — aligning with the government’s goal for a majority-CNG vehicle fleet by 2050.

This is in addition to seven CNG stations already under construction, mobile CNG units being rolled out, Rashal Energies’ plan for 30 CNG stations, and Gazprom’s reported market entry. The transport fuel mix is evolving fast — and CNG infrastructure can be built in months, not years.


Why This Matters for Gas Demand

Even at a conservative average of 2 MMscf/d per site, if a significant share of these 109 permitted stations are CNG-capable, they could add well over 150 MMscf/d of demand once operational. This is highly modular demand that can scale quickly, complementing larger, longer-lead projects.

CNG is only one part of the demand stack. Other confirmed and emerging gas consumers include:

  • Aspin Energy / Escom Power Plant (Malawi) – 142 MW natural gas-fired plant using Tanzanian gas from March 2026 (~30 MMscf/d)

  • Rocky Mountain GTL Plant – $420M gas-to-liquids facility producing diesel and jet fuel (~25–30 MMscf/d)

  • ESSA Fertilizer Plant – Targeting 70 MMscf/d by 2027–2029, potentially supplementing Mnazi Bay supply

  • Mtwara LNG Project – $4.5B state-backed export and regional distribution hub, starting at 400 MMscf/d and scaling to 1,200 MMscf/d, with Ntorya named as primary supplier

Taken together, these represent layered, long-term, and scalable demand — reducing offtake risk for upstream producers and creating multiple market channels.


Aminex’s Strategic Position

For Aminex and its carried 25% interest in the Ntorya field, the convergence of infrastructure rollout and industrial demand is transformational:

  • Fully carried to ~$40M net, removing capital burden in development

  • Favourable PSA terms compared to industry norms, increasing effective revenue share

  • Pipeline to Madimba under construction, de-risking first gas timelines

  • Direct link to high-value offtake via Mtwara LNG and industrial markets

With scalable production — and the ability to grow beyond 280 MMscf/d — Aminex sits at the heart of Tanzania’s domestic energy transition and export growth ambitions.


Investor View: More Than Just “Potential”

The EWURA permit wave is not an aspirational policy statement — it is a regulatory step that clears the way for real companies spending real capital on fuel and gas infrastructure. Add in signed EPC contracts, pipeline works, and the state-backed LNG plan naming Ntorya as a primary supplier, and you have tangible progress.

Near-term catalysts include:

  • Physical confirmation of pipeline ground-breaking

  • PURA approval to accelerate the Chikumbi-1 rig tender

  • Additional industrial offtake agreements

With the current share price still below 2p, these could drive sharp re-ratings.


Bottom line:
Tanzania’s downstream build-out, rising industrial gas prices, and LNG export positioning create a market capable of absorbing — and paying premium rates for — every molecule Ntorya can produce. For Aminex, the building blocks for a multi-year growth story are already falling into place.

Friday, 25 July 2025

Aminex AGM Signals Acceleration:

Aminex AGM Signals Acceleration: CH‑1 Before Pipeline, Phase 2 Plans, and Market-Ready Momentum

For me, this year’s Aminex AGM marked a fundamental shift—not just in tone, but in tempo.

For the first time in years, the Board spoke with conviction and clarity. No ambiguity. No hedging. Just a clear message: Ntorya is entering execution mode, and the drill is coming before the pipeline is complete!


🔩 “CH‑1 Will Be Drilled Before the Pipeline Is Completed”

No hesitation. No caveats. That is now the base case.

The Board confirmed that all parties—TPDC, ARA, Aminex, and the Tanzanian government—are aligned and urgently pushing to get CH‑1 drilled. PURA’s involvement has been specifically to accelerate rig tendering.

Rig tendering is imminent. While a shared rig with M&P is being discussed, other rigs are in the running—and the Board made it clear that M&P’s timeline would be too late (mid‑2026). In other words: the M&P option may just be negotiation leverage.

Bottom Line:

  • TPDC is “pushing like crazy”

  • CH‑1 is on the clock

  • Phase shift confirmed. Execution starts now.


📈 CH‑1 Targeting 50 MMscf/d Flow Rate

The Board corrected the assumption of 20 MMscf/d per well:

“CH‑1 is expected to flow at ~50 MMscf/d.”

This well targets a thicker section of the reservoir with stacked pays, including Unit 3—making it much higher impact than NT‑2, which flowed 17 MMscf/d under constrained conditions.

A new CPR (Competent Person’s Report) is expected after CH‑1 or Phase 1 drilling, with upgraded reserves, production profiles, and valuation.


💧 Condensate Could Add +15% to Project Value

The Board confirmed condensate volumes could deliver ~15% additional value—clean margin revenue, possibly hundreds of millions over the field’s life.


💸 Gas Pricing Has Built-In Upside

Two key revenue drivers:

  1. Inflation clause built into the GSA

  2. Higher prices for industrial offtake vs. utility rates

With industrial gas demand rising in Tanzania, Aminex could see surprise upside on realised pricing.


🔗 ARA Wants Aminex to Stay

Why hasn’t Aminex been bought out or diluted? The Board explained:

  • ARA is happy with 75% and sees value in Aminex’s public listing

  • The listing provides transparency, valuation, and investor reach

  • If ARA wanted Aminex gone, it would’ve happened already


🚀 Phase 2 Strategy: 280 MMscf/d or Bust

The operator isn’t stopping at Phase 1:

  • 6 more wells planned

  • Second pipeline to Madimba

  • Expanded processing facility

“140 MMscf/d won’t adequately drain the field. 280 MMscf/d brings reserves into production within the license life.”

This is operator-led strategy, not speculative dreaming. Ntorya is being built as a national energy asset.


🏦 Funding Runway + Cash Flow Timing

  • Aminex has used ~50% of its facility, with ~$1.5m available

  • Burn rate: ~$1.5m/year, so fully funded for 12 months

  • First cash flow expected ~September 2026, once the pipeline is commissioned

Payments will be a mix of USD and Tanzanian Shillings.


🧾 TPDC to Take 60 MMscf/d Initially

TPDC has committed to 60 MMscf/d of initial offtake, with the rest going to industrial customers. Virtual pipeline, LNG, CNG, mining, manufacturing are all in ARA’s strategy.

Demand is not a concern. Discussions are already underway.


🧪 NT‑2 Test Still Going Ahead

Despite the focus on CH‑1, the NT‑2 well test is still scheduled before pipeline commissioning. It will confirm deliverability and gas composition (expected 3% CO₂ content—low and manageable).


📌 TPDC Back-in Rights Still at 15%

The 15% back-in right has not been exercised yet, and that remains the limit under the PSA. Any change would be procedural and expected.


🔍 Kiliwani, Nyuni, and Exploration Strategy

  • Kiliwani is on hold, but still has potential. Seismic planned.

  • Nyuni is “too risky” for now. Scale-down and partnership are in progress.


📣 PR Reset and New Valuation Coming

The Board acknowledged past silence and promised a PR reset:

  • Regular updates to resume

  • Journalists engaged

  • New Shard Capital valuation incoming—expected to be more bullish


🧠 Final Word: It’s Not “If” Anymore

This AGM didn’t just confirm:

  • CH‑1 before pipeline completion

  • 50 MMscf/d flow potential

  • Phase 2 expansion strategy

It changed the tone of the entire project.

We’re not asking if Ntorya will deliver.
We’re asking how fast, how big, and how long we stay invested.


The above report comes thanks to the attendance at the AGM by Prospero 

Aminex Model Update 25th July 2025

 

📌 Recent AGM & Operational Update

According to the 2025 AGM feedback and RNS issued on 17 July 2025:

  • Chikumbi‑1 drilling has been moved forward and is now scheduled before pipeline completion, meaning drilling activity may precede first gas pipelines.

  • Pipeline construction is set to begin by end of July 2025, with commissioning expected by July 2026



🧾 Does This Change the Revenue-Sharing Model?

Not materially. The PSA and GSA remain confidential, but public disclosures confirm they follow the favourable 2022 gas fiscal addendum:

These terms remain in force regardless of drilling sequence

Consultations with ARA/TPDC indicate the PSA’s exceptional commercial terms heavily benefit JV partners, especially as Aminex is carried through development.


✅ Implications for Value and Share Price

Operational Acceleration:

  • Drilling CH‑1 early could fast-track resource confirmation, potentially moving SP catalysts forward by months.

  • Rig tender launch by mid-August 2025 now likely to precede major pipeline coverage—earlier drilling → earlier data → earlier valuation triggers.

Revenue Model Intact:

  • Offtake structure, cost recovery profile, and contractor split remain exactly as modeled.

  • No change in Aminex’s fiscal share or exposure—only impact is timing of cash flows.

Share Price Impact:

  • Expect possible 20–50% stock moves on positive CH‑1 updates or rig contract awards.

  • Timeline for first gas remains mid‑2026; commercial ramp-up projections still valid.

  • Earlier drilling may shift upward price momentum ahead of pipeline completion.


🧪 Recalibrated Forecast Table

MilestoneApprox. TimingPotential SP Upside (%)Commentary
CH‑1 Drill Contract AwardMid‑Aug 2025+20–30%Accelerates early-chapter SP drivers
CH‑1 Spud / Rig MobilisationLate 2025+30–50%Confirms resource & de-risks field plan
Pipeline Construction UnderwayJuly–Aug 2025+20–30%Narcot entry into execution phase
Pipeline CommissioningJuly 2026+50–100%Gas generation capability solidified

📌 Final Word

  • Yes, shifting CH‑1 earlier is a meaningful operational acceleration—pushing several SP value drivers forward.

  • No, it doesn’t alter Aminex’s revenue-sharing model or fiscal upside.

  • The core valuation remains valid—but the timing of expected SP triggers and cash flows is now more immediate.

Thursday, 17 July 2025

Aminex RNS Ntorya Operations Update - Rig Tender Strategy

 Today 12:00

RNS Number : 5111R
Aminex PLC
17 July 2025
 

17 July 2025

 

Aminex plc

 ("Aminex" or "the Company")

 

Ntorya Operations Update

 

Aminex, the oil and gas exploration and development company focused on Tanzania, is pleased to announce the following operations update on the Ntorya development:

· At the end of last week, the Tanzania Petroleum Development Corporation (TPDC) formally notified the operator of the Ntorya development (ARA Petroleum Tanzania Limited (APT)) that construction of the pipeline from the Ntorya gas field to the Madimba gas processing plant (the Pipeline) shall commence in July 2025 and is scheduled to be completed and commissioned by the end of July 2026. The Ntorya-2 well will provide gas once the Pipeline is commissioned.

 

· Earlier this week, APT presented a tender strategy to the Petroleum Upstream Regulatory Authority (PURA) for contracting a rig to drill the Chikumbi-1 well and perform a workover on the Ntorya-1 well, along with all related services. PURA requested this strategy to expedite the tendering process. Once APT receives approval from PURA, it will immediately issue the rig tender and tenders for other necessary services, expecting to do so no later than mid-August 2025.

Charles Santos, Executive Chairman of Aminex commented:

"We are delighted that work on the pipeline will commence this month, marking the start of the construction phase of the Ntorya Gas Development. With a plan to complete the Pipeline by July 2026 and expectation of starting a rig tender process very soon, the project is well on its way to producing first gas next year.

We are grateful to the TPDC, PURA and other agencies, which have backed the Government of Tanzania's strong commitment to our project with their hard work. And we thank APT as the operator for managing the dynamic work streams to reach this milestone.

As the discoverer of the Ntorya Gas Field and founding partner in the development, we have long believed the project will be a gamechanger for Tanzania's energy landscape. Gas from the first phase of development will be staying in Tanzania to help power homes, boost industrial development and the regional economy and replace dirtier fuels such as coal and charcoal. This has long been our vision and now we are very excited to be so much closer to realising that vision."

 

For further information:

 

Aminex PLC

+44 203 355 9909


Charles Santos, Executive Chairman

Knights Media & Public Relations

+44 203 653 0200


Jason Knights, Sabina Zawadzki

 

 

Davy

+353 1 679 6363


Brian Garrahy

 

 

Shard Capital

+44 20 7186 9952


Damon Heath

 

 

Notes to Editors:

The Ntorya Development Licence area lies adjacent to a region containing supergiant world-class LNG projects, extending from offshore Tanzania into Mozambique waters to the south. The JV partners intend to produce Ntorya gas into the growing domestic gas market, helping to alleviate energy poverty and boost the energy transition in Tanzania.

Aminex, with a 25% non-operated interest, is carried throughout the ongoing work programme to a maximum gross capital expenditure of $140 million ($35 million net to Aminex). The carry is expected to see the Company through to the commencement of commercial gas production from the Ntorya field at zero cost to the Company.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 