Tuesday, 30 September 2025

Aminex Turns the Corner: First Gas in Sight and Fresh Life for Kiliwani

Positive signals from the latest Interim Management Report

Friday’s RNS marked a genuine turning point for Aminex. For the first time in years, management has not only confirmed Ntorya’s rapid progress into construction — but also opened the door once again to future activity at Kiliwani and Nyuni. That’s a big statement of intent, and it suggests the company is in a far stronger and more confident position than many might have expected.

A Stronger Foundation

Executive Chairman Charles Santos set the tone clearly:

“The Ntorya Gas Development has now advanced definitively into its construction phase, following the award of the Ntorya-Madimba pipeline contract. This milestone has in turn catalysed wider activity on the ground and across the project.”

This is not vague promise; it is pipeline contracts awarded, procurement already under way, and a clear timetable: pipelaying begins January 2026, with first gas targeted for mid-year.

Ntorya isn’t a small play. With a 35-year horizon, production is expected to hit a plateau of 280 MMcfd — more than Tanzania’s current total output. Initial production from NT-1, NT-2 and CH-1 alone is expected at 60 MMcfd, with revenues for Aminex to follow swiftly thanks to the free carry deal still in place.

The Importance of Seismic and Planning

APT’s expanded Field Development Plan was built on the 338 km² of 3D seismic shot in 2022–2023. This data has given unprecedented clarity, derisking the next phases and cementing Ntorya as the largest onshore gas development in East Africa.

For Aminex shareholders, this means a foundation not just for near-term revenue, but for sustained value over decades.

Kiliwani and Nyuni Back on the Agenda

Perhaps the most striking part of the statement was this:

“Once Ntorya production and revenues are established, Aminex expects to refocus on the Kiliwani North Development Licence and the Nyuni Area PSA.”

This is the first time in several years that Kiliwani has featured in company messaging. The fact it is being brought back into the conversation now signals renewed ambition. A targeted 3D seismic programme at Kiliwani and a reshaped Nyuni work programme could add a further leg of growth — and importantly, the confidence to talk about them is itself a sign of strength.

Lean and Supported

Financially, Aminex remains disciplined. Operating costs are just $0.92m for the period, with Eclipse Investments continuing to provide backing via a $3m working capital facility. Crucially, the 2020 farm-out still means Aminex is carried through development costs until revenue arrives — removing risk and preserving upside.

Outlook: Momentum and Delivery

The company closes the half-year with momentum firmly on its side. The preparatory phase is complete. Construction is under way. Gas sales are on the horizon. And for the first time in years, Aminex is openly signalling its intention to go beyond Ntorya.

That is why Friday’s RNS matters. It’s not just about timelines and contracts — it’s about confidence. The mention of Kiliwani is a reminder that Aminex’s story is bigger than one field, and that management is now looking further down the road with optimism.

Wednesday, 27 August 2025

Aminex RNS: Ntorya Operations Update Confirms Pipeline and Rig Milestones

Procurement for the Ntorya–Madimba pipeline begins, groundwork scheduled for January, while PURA approves the rig tender strategy.


Key Highlights from Today’s RNS

  • Pipeline Progress:

    • Contractors have begun procurement of pipe and equipment for the 35 km pipeline linking Ntorya to the Madimba gas processing plant.

    • Mobilisation of construction equipment will begin in September 2025.

    • Groundwork and pipelaying are scheduled to commence in January 2026, with completion targeted by July 2026.

  • Condensate Value Addition:

    • Discussions are under way regarding the processing and storage of condensate volumes from Ntorya — an additional revenue stream beyond gas sales.

  • Rig Tender Milestone:

    • The Petroleum Upstream Regulatory Authority (PURA) has approved the tender strategy for contracting a drilling rig.

    • The rig will be used to drill Chikumbi-1 (CH-1) and perform a workover on Ntorya-1 (NT-1).

    • Operator APT will request expressions of interest from service contractors next week.


Why This Matters for Investors

This RNS confirms that multiple strands of Ntorya’s development are advancing in parallel:

  • Pipeline: With procurement already under way and a firm mobilisation schedule, the long-discussed link to Madimba has moved from planning to delivery. A clear timeline to completion by July 2026 provides investors with visibility.

  • Rig Tender: PURA’s approval is a regulatory green light that allows the operator to advance into contractor engagement. The drilling of CH-1 and the NT-1 workover will expand production capacity beyond NT-2, underpinning volumes for the GSA.

  • Condensate: Monetisation of condensate offers upside beyond gas sales, increasing the value of the project.

Together, these steps strengthen confidence that Ntorya is firmly on its way to first gas, with strong backing from TPDC, PURA, and APT.


Aminex Management Comment

Charles Santos, Executive Chairman, highlighted:

“Our discussions with the TPDC and the operator have been extremely fruitful, and we are delighted that activity on the Pipeline is proceeding as planned… PURA has approved the tender strategy, allowing APT to begin the tender process. These developments demonstrate again the Government of Tanzania’s strong commitment to this project.”


Investor Takeaway

This update provides:

  • Visible progress on the pipeline, with equipment procurement already started.

  • Firm dates for mobilisation (Sept 2025), groundwork (Jan 2026), and completion (July 2026).

  • Regulatory approval clearing the way for the rig tender and the next phase of drilling.

  • Condensate upside adding to the project’s revenue profile.

For shareholders, this RNS delivers the clearest evidence yet that Ntorya’s development is advancing on multiple fronts, backed by Tanzania’s institutions and operator commitment.

Monday, 28 July 2025

🔧 East Africa’s Energy Catalyst: Ntorya–Madimba Pipeline Breaks Ground

 The long-anticipated pipeline that will unlock Tanzania’s Ntorya gas field is finally moving into construction. This month, July 2025, marks the official start of the Ntorya–Madimba pipeline, a game-changing infrastructure project for East Africa’s energy future.


🛠️ Pipeline Construction Begins – July 2025

The Tanzania Petroleum Development Corporation (TPDC) has awarded the Engineering, Procurement, and Construction (EPC) contract to China Petroleum Pipeline and China Petroleum Technology & Development Corporation—two heavyweights in global energy infrastructure.

  • Construction Start: July 2025

  • Commissioning Target: End of July 2026

  • Length: ~35 km

  • Purpose: Connect the Ntorya gas field to the Madimba gas processing plant


📍 What This Pipeline Unlocks

This pipeline is more than just a piece of steel in the ground. It’s the central artery that will:

  • Enable first commercial gas from the Ntorya-2 well

  • Prepare for Ntorya-1 workovers and future production scaling

  • Lay the foundation for Phase 2 field expansion—up to 280 MMscf/d

Once completed, the pipeline will allow gas to flow from the Ruvuma basin into Tanzania’s domestic energy grid, supporting industrialisation, reducing reliance on imports, and opening doors for export via LNG or CNG.


🛢️ Strategic Value for Aminex and ARA Petroleum

For joint venture partners Aminex PLC and ARA Petroleum Tanzania, this project is the key milestone needed to shift from resource holder to revenue generator. With first gas expected in mid-2026, the clock is ticking on the transition from exploration to monetisation.


🧱 The Bigger Picture

This pipeline doesn’t stand alone—it’s part of a comprehensive infrastructure upgrade that includes:

  • The upcoming Chikumbi‑1 well

  • Workover and tie-in of Ntorya‑1

  • Expansion of the Madimba plant

  • Future development of a second pipeline and six additional wells under Phase 2


📣 Final Takeaway

With construction now officially launching, the Ntorya project has crossed the line from planning to execution. Investors, partners, and stakeholders can now begin counting down to first gas—and with it, the arrival of revenue, reserves growth, and value realisation.

East Africa’s gas future is no longer just potential—it’s under construction.

Sunday, 27 July 2025

Aminex Ignites: Early Drilling, Accelerated Pipeline, and Momentum Into 2026

 Here’s the latest weekly summary of Aminex PLC developments, incorporating official updates and Tanzanian press coverage:


Aminex Ignites: Early Drilling, Accelerated Pipeline, and Momentum Into 2026

The tempo has changed—and this time, it’s real.

Following this week’s AGM and official field updates, Aminex has entered the execution phase of the Ntorya development. With shareholder confidence rising and new operational details confirmed, the value case is solidifying. For investors watching from the sidelines, the clock is ticking.


🔧 Chikumbi‑1 to Be Drilled Before Pipeline Completion

In a significant pivot from prior expectations, the Aminex Board confirmed that Chikumbi‑1 (CH‑1) will be drilled before the Ntorya–Madimba pipeline is completed.

Why does this matter?

It means:

  • CH‑1 results will be known well ahead of first gas

  • The market will re-rate on resource confirmation, not just revenue

  • Aminex can issue an updated CPR sooner, likely boosting reserves and valuation

This decision wasn’t speculative—it’s now the base case, supported by all project partners, including TPDC and PURA.


🛠️ Pipeline Construction Timeline Compressed

While the official guidance says 12 months, industry talk suggests the pipeline could be completed in as little as 8 months. That would shift commissioning forward into Q1 or Q2 2026, compressing the timeline for Aminex to receive first cash flow from gas sales via NT‑2.


💥 What’s Coming and Why It Matters

The execution roadmap is now clear and packed with near-term catalysts:

  • Rig tender imminent (August 2025)

  • CH‑1 spud likely in late 2025

  • NT‑2 well test scheduled pre-pipeline

  • New CPR and Phase 2 planning in 2026

  • Condensate uplift + industrial pricing flexibility

Each of these events has the potential to drive share price momentum—independently.


🧮 Production Expectations Skyrocket

The Board confirmed that CH‑1 is expected to flow at ~50 MMscf/d—more than double prior assumptions. That’s because the well will target thicker, stacked reservoirs, including untapped units.

This single well could anchor Phase 1 delivery and define Phase 2 scalability.


💧 Condensate Could Add +15% to Field Value

Condensate volumes are now forecast to provide an additional 15% value uplift—a high-margin revenue stream not yet fully priced into market expectations.


💸 Gas Pricing Includes Upside Leverage

Two revenue-enhancing features:

  • Inflation indexing in the GSA

  • Premium pricing from industrial offtakers

With Tanzania’s mining and manufacturing sectors expanding, Aminex and ARA are well positioned to capture higher-than-utility tariffs.


🛡️ Strong JV Dynamics—ARA Wants Aminex In

Despite owning 75%, ARA isn’t pushing Aminex out. The Board made it clear: the public listing provides transparency, credibility, and valuation clarity that ARA finds valuable.

If a buyout were coming, it would’ve happened already.


📊 Phase 2 = 280 MMscf/d

Aminex’s long-term role just expanded. With up to 16.4 tcf unrisked gas in place, TPDC and ARA have revealed plans for:

  • 6 more wells

  • A second pipeline

  • Expanded processing capacity

The target is now 280 MMscf/d, not 140. Ntorya is being positioned as a national energy hub.


🪙 Financial Runway and First Cash Flow

Aminex has sufficient funds to maintain operations until first cash flow expected by mid‑2026. With NT‑2 as the first producer and CH‑1 to follow, this positions Aminex for sustainable profitability.


🔚 Final Word

This isn’t just another speculative frontier gas story.

  • The rig is coming.

  • The drill will happen before gas flows.

  • The pipeline may finish early.

  • And Aminex has clear upside leverage—both technically and commercially.


📈 Projected Share Price Catalyst Chart

Each catalyst represents a standalone opportunity for revaluation. And as the timeline accelerates, the market’s response could become even more aggressive.

If you’re looking for asymmetric upside in frontier energy, Aminex just moved into the fast lane.

Thursday, 17 July 2025

Aminex RNS Ntorya Operations Update - Rig Tender Strategy

 Today 12:00

RNS Number : 5111R
Aminex PLC
17 July 2025
 

17 July 2025

 

Aminex plc

 ("Aminex" or "the Company")

 

Ntorya Operations Update

 

Aminex, the oil and gas exploration and development company focused on Tanzania, is pleased to announce the following operations update on the Ntorya development:

· At the end of last week, the Tanzania Petroleum Development Corporation (TPDC) formally notified the operator of the Ntorya development (ARA Petroleum Tanzania Limited (APT)) that construction of the pipeline from the Ntorya gas field to the Madimba gas processing plant (the Pipeline) shall commence in July 2025 and is scheduled to be completed and commissioned by the end of July 2026. The Ntorya-2 well will provide gas once the Pipeline is commissioned.

 

· Earlier this week, APT presented a tender strategy to the Petroleum Upstream Regulatory Authority (PURA) for contracting a rig to drill the Chikumbi-1 well and perform a workover on the Ntorya-1 well, along with all related services. PURA requested this strategy to expedite the tendering process. Once APT receives approval from PURA, it will immediately issue the rig tender and tenders for other necessary services, expecting to do so no later than mid-August 2025.

Charles Santos, Executive Chairman of Aminex commented:

"We are delighted that work on the pipeline will commence this month, marking the start of the construction phase of the Ntorya Gas Development. With a plan to complete the Pipeline by July 2026 and expectation of starting a rig tender process very soon, the project is well on its way to producing first gas next year.

We are grateful to the TPDC, PURA and other agencies, which have backed the Government of Tanzania's strong commitment to our project with their hard work. And we thank APT as the operator for managing the dynamic work streams to reach this milestone.

As the discoverer of the Ntorya Gas Field and founding partner in the development, we have long believed the project will be a gamechanger for Tanzania's energy landscape. Gas from the first phase of development will be staying in Tanzania to help power homes, boost industrial development and the regional economy and replace dirtier fuels such as coal and charcoal. This has long been our vision and now we are very excited to be so much closer to realising that vision."

 

For further information:

 

Aminex PLC

+44 203 355 9909


Charles Santos, Executive Chairman

Knights Media & Public Relations

+44 203 653 0200


Jason Knights, Sabina Zawadzki

 

 

Davy

+353 1 679 6363


Brian Garrahy

 

 

Shard Capital

+44 20 7186 9952


Damon Heath

 

 

Notes to Editors:

The Ntorya Development Licence area lies adjacent to a region containing supergiant world-class LNG projects, extending from offshore Tanzania into Mozambique waters to the south. The JV partners intend to produce Ntorya gas into the growing domestic gas market, helping to alleviate energy poverty and boost the energy transition in Tanzania.

Aminex, with a 25% non-operated interest, is carried throughout the ongoing work programme to a maximum gross capital expenditure of $140 million ($35 million net to Aminex). The carry is expected to see the Company through to the commencement of commercial gas production from the Ntorya field at zero cost to the Company.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END

Thursday, 10 July 2025

TPDC Construction Launch Signals Green Light for Ara / Aminex Ntorya Development

Pipeline Momentum Builds as Dry Season Window Opens

With the EPC contract for the Ntorya–Madimba pipeline formally awarded in early July 2025, attention now shifts to execution—and there are growing signals that construction is set to begin imminently, taking full advantage of Tanzania’s current dry season.

⚙️ Operational Readiness: More Than Just an Announcement

While markets welcomed the EPC award with a sharp share price jump, the underlying operational reality suggests far deeper progress than the announcement alone implies. Aminex and its joint venture partner ARA Petroleum Tanzania (APT) appear to have methodically prepared for this moment over the past several months.

  • Drilling infrastructure is already in-country: Pipework is stored at one of the Ntorya well sites, and the wellhead for the key Chikumbi‑1 (CH‑1) well has been ready for shipment for some time.

  • The field development sequence is optimised and staged: NT‑2 will be the first well connected, using mobile testing equipment (no rig required), followed by drilling CH‑1, and later a rig-based workover of NT‑1 using the same equipment.

  • This sequencing minimises logistical overlap and supports the planned ramp-up of production toward 140 MMscfd over the medium term.

🛠️ EPC Mobilisation: Signals Point to Immediate Start

Although the formal EPC announcement came in July, a series of operational indicators strongly suggest that mobilisation has been underway behind the scenes for some time:

  • The rapid commencement of contractor recruitment for local positions within days of the announcement indicates that staffing plans were prepared well in advance.

  • This is consistent with infrastructure projects where preferred bidders, once informally selected, often begin early-stage logistics, equipment procurement, and site planning before the formal signing—especially when delivery windows are tight.

  • The public commitment to completing the project within 12 months adds weight to this view. Such a timeline would not be credible without supply chain arrangements already in motion and construction strategies finalised.

In short, while the market may only now be digesting the announcement, the project itself appears to be months ahead in planning, and construction is likely to commence during this dry season—between late July and September 2025.

🌧️ Why Not Wait?

Delaying construction into Q4 would push key trenching and infrastructure work into Tanzania’s rainy season, increasing costs and operational risk. That would conflict with the EPC contractor’s guarantee of delivery within a 12-month window—making it far more rational to act now, while ground conditions are favorable.

Additionally, well logistics, permits, seismic studies, and land access issues are largely resolved, meaning that the path is clear for field execution.

📈 Market Implications: A Potential Re-Rating Catalyst

Should Aminex or the EPC contractor formally announce mobilisation in the coming weeks—whether via photos, press updates, or site commissioning—it could act as a major share price catalyst, adding to the already strong momentum from the EPC award.

Historical market behaviour suggests such a trigger could generate a further 10–20% upside in the near term, as it would materially de-risk the timeline to first gas in 2026.


✅ Final Word

With project hardware in-country, well sequences defined, and staffing underway, Aminex and ARA appear strategically positioned to begin construction within the current dry season. For shareholders and market watchers, the next catalyst is clear: physical mobilisation on the ground. And by all indications, that milestone may be just days or weeks away.


Monday, 1 May 2023

RNS Aminex

 Fri, 28th Apr 2023 18:13

RNS Number : 9593X
Aminex PLC
28 April 2023
 

28 April 2023

 

FINAL RESULTS for year ended 31 December 2022 AND ANNUAL REPORT

 

Aminex PLC ('Aminex' or the 'Company') is pleased to announce its audited financial results for the year ended 31 December 2022.

 

Highlights

 

Outlook:

• The operator of the Ruvuma PSA, ARA Petroleum Tanzania Limited ("APT") continues to progress operations at the Ntorya field, with the following planned for 2023:

o  Two-week well testing programme on NT-2, utilising a mobile testing unit, principally to sample the gas and establish an accurate measurement of the gas composition, required for the design of in-field processing facilities and the export pipeline to the Madimba Gas Plant

o  Conclusion of negotiations and execution of a Gas Sales Agreement

o  Finalisation of terms for the construction of (i) an export pipeline from Ntorya to the Madimba Gas Plant to accommodate gas by October 2023; and (ii) in-field gas gathering and processing facilities

o  Entering into a rig contract to (i) drill, test and complete the Chikumbi-1 well ("CH-1") as a gas producer; and (ii) workover and recomplete the NT-1 well as a gas producer

o  Following the processing of 3D seismic data, an optimal well location has been determined for the CH-1 well

• APT has also submitted a near final Field Development Plan to the Tanzania Petroleum Development Corporation which, upon approval, will lead to the issuance of a Development Licence for the Ntorya field

• Orca Energy, though its subsidiary, Pan African Energy Tanzania, has commenced its 3D seismic acquisition programme over its Songo Songo licence which includes an incursion of 12.5km² over part of the Kiliwani North Development Licence ("KNDL") at no cost to the KNDL parties. The acquisition programme is expected to be completed by Q3 2023.

 

During 2022:

• APT completed the 3D seismic programme over the Ntorya area in October 2022

• An Addendum to the Ruvuma PSA setting out the fiscal terms for gas (as opposed to oil) production from the Ruvuma PSA was signed by all parties on 25 November 2022

• Successfully raised approximately US$4.35 million (approximately £3.30 million) before expenses in April 2022 to fund the Company to the expected receipt of revenue from first gas production at the Ntorya field

• Company now debt-free following the share placement

• Ruvuma PSA Farm-Out Carry of US$35 million covered Aminex for all 2022 Ruvuma costs with US$30.72 million of the Carry remaining as at 31 December 2022

• Further reduction in gross G&A costs (before one-off costs and exceptional items) to US$1.46 million per annum in 2022, a reduction of 19% from 2021 and a significant reduction from 2018 levels when cost control measures commenced

• Loss for the year of US$4.06 million (2021: loss of US$8.56 million)

 

The Annual Report may be viewed on the Company's website www.aminex-plc.com by clicking on the following link:

 

Aminex PLC Annual Report 2022

 

The Company will announce details of the Annual General Meeting in due course.

 

Paper copies of the Annual Report together with the Notice of Annual General Meeting, including the Form of Proxy, will be mailed shortly to those shareholders who have elected to receive paper copies.

 

The Executive Chairman's Statement from the Annual Report follows below:

 

Executive Chairman's Statement

 

Dear Shareholder,

 

We believe 2023 will be a watershed year for our Company, with multiple macro and local developments converging to produce shareholder value.

 

Since my last Executive Chairman's Statement, energy prices have remained significantly higher than their April 2020 historic lows, with a Brent crude oil spot price average of US$100 per barrel for 2022. The higher energy prices, linked to the lack of investment in new oil and gas projects, sanctions against Russian oil and gas exports, and growing demand in the developing world, are projected to continue into the near and mid-term. Higher energy prices and shortages have emphasised the importance of fossil fuels, particularly natural gas, for the coming decades as an essential and cleaner energy source for global economic development. Moreover, the macro-political uncertainty and significant demand for energy in the developing world will, we believe, translate into continued growing demand for gas globally.

 

In Tanzania, we stand by last year's assessment of the country's significantly improved commercial and business climate. Moreover, we see the business climate continuing to improve. Specifically, the Tanzanian authorities appear fully committed to natural gas development and are making considerable efforts to accelerate natural gas production from Ruvuma. Moreover, the Tanzanian authorities, aware of their need to increase energy production to grow the country's economy, have embarked on further industrial development. These efforts include planning and constructing numerous facilities along existing gas delivery infrastructure directly connected to or near our Tanzanian assets which will increase local gas demand substantially in the short to medium term. In addition, discussions have been reported between Tanzanian Government officials and their counterparts in neighbouring countries exploring the possibility of securing a long-term gas supply from Tanzania, which will contribute to future gas demand in the East African region. These positive developments in the Tanzanian gas sector bode well for the commercialisation of our assets soon.

 

Non-Operating Strategy

 

Our move from an operating to a non-operating business has enabled the Company to de-risk while anchoring shareholder value by:

1. Shifting operational risk on our most valuable asset, Ruvuma, to ARA Petroleum Tanzania Limited ("APT"), a highly competent, capable, and well-funded operator.

2. Further de-risking by APT to accelerate gas production, targeting October 2023, shifting the operational narrative of Ruvuma from a dependence on the spudding and outcome of the Chikumbi-1 well ("CH-1") to a more anchored and broader development effort as we move toward early gas production.

3. Reducing our operating expenses and overhead significantly to protect the Company while the project is still not generating cash.

4. Successfully acquiring the necessary funds via our equity placing in April 2022 to ensure our running costs are covered (before one-offs and exceptional items) until receipt of Ruvuma revenues commences.

 

Aminex's non-operating strategy has made it a stronger, more secure company with a low-cost base and an entirely carried position on Ruvuma and is debt free. It provides a solid financial situation until the commencement of cash flow receipts from Ruvuma. Moreover, APT has reduced the time to cash flow receipts with an accelerated gas production plan, which is strongly supported by the Tanzanian Government and aligned with its need for gas in the short and medium term. The success of this strategy is now in sight as it appears Ruvuma's revenue will come significantly sooner than our original projection.

 

Ruvuma PSA

 

The Farm-Out completed with APT in October 2020 carries the Company to material levels of production and revenue without the need to return to shareholders for additional funding for the development of the Ntorya field. This revenue is now projected sooner, given the acceleration of production agreed upon between the operator and the Tanzania Petroleum Development Corporation ("TPDC"). The Company holds a 25% interest in the Ruvuma PSA with a US$35 million carry of its share of costs. The carry, equivalent to US$140 million of gross field expenditure, is expected to see the Company through to potentially significant gas production volumes with commensurate revenues. The Farm-Out is a result of successful exploration and evaluation work by Aminex, which recognised the underlying value and opportunities in the Ruvuma Basin, while effectively pivoting to a non-operating role to ensure full exploitation of resources and de-risking the Company.

 

With the acquisition of 3D seismic data completed in November 2022 and the culmination of seismic data processing in March 2023, we now have an optimal well location for CH-1 grounded in significant 3D seismic data. We anticipate the spudding of CH-1, and a workover of the Ntorya-1 well ("NT-1") later this year. We also expect a completed well-test of the Ntorya-2 well ("NT-2") soon, providing information that will facilitate the construction of a 35-kilometre pipeline to the Madimba gas processing facility by the Government of Tanzania. The full 3D seismic results will be available by mid-2023 and will permit a thorough revision of the gas reserve and resource potential for the field later in the year. Finally, we expect to sign a Gas Sales Agreement and obtain a Development Licence for the Ntorya Area, securing the long-term development of Ruvuma imminently.

 

2023 will be a watershed year for the development of Ruvuma with the completion of the 3D seismic survey, the monetising of this extensive gas resource through production into existing infrastructure and transportation to an established power and industrial market in Tanzania. Since acquiring operatorship, APT has continued demonstrating focused determination, technical prowess, and a total commitment to the project.

 

Kiliwani North and Kiliwani South - Kiliwani North Development Licence ("KNDL")

 

Orca Energy, via its subsidiary PanAfrican Energy Tanzania ("PAET"), is expected to complete its acquisition of 3D seismic over its Songo Songo license area by Q3 2023. The new 3D seismic programme includes an incursion of 12.5 km2 over part of the KNDL that borders the Songo Songo field to the west as part of their full-field survey. The data, at no cost to the KNDL partners, will be valuable in identifying fault trends, improving reservoir definition, and understanding the Kiliwani North and South structures. We expect to receive processed data by the end of 2023 or early 2024, allowing Aminex to re-evaluate further prospectivity of KNDL and opportunities for further development. It will enable a more robust discussion with future partners to operate the asset and secure additional funding through a farm-out. We have continued with impairment of the Kiliwani North and Kiliwani South assets during the year. We will update shareholders with progress in due course.

 

Nyuni Area PSA

 

In April 2022, we commenced a process with the relevant authorities in Tanzania to return the licence, given our belief that although the Nyuni Area acreage offers upside exploration potential to complement the development projects at Ntorya and Kiliwani North, the significant risks of exploration and the lack of a farm-out partner was far too much risk for a company of our size. The Tanzanian authorities requested that we continue efforts to secure a farm-in partner over the next year, to which we have agreed.

 

Cost Cutting

 

We continued to cut costs and reduce corporate overheads, including reducing General and Administrative expenses ("G&A"). The Company saw a small increase of 5% in headline G&A for the year of US$0.14 million compared to 2021, but a decrease in base running costs (which excludes non-cash and one-off items), before recharges, to US$1.46 million for the year, compared with US$1.81 million for 2021, a reduction of 19% (see Finance Review for further details). The cumulative annual reductions in the Company's gross G&A costs (before one-off expenses and exceptional items) to US$1.46 million per annum in 2022 represents a 72% reduction from 2018 levels. Through these cost saving initiatives, the Company has established an appropriate structure of capabilities and competencies that match the current requirements of the business with a more flexible approach that de-risks our business and can help create or attract strategic opportunities.

 

Outlook and Funding

 

On 1 April 2022, we announced the fully subscribed placement for approximately US$4.35 million, providing an essential pillar in our effort to de-risk and anchor value. The funds ensure a solid financial foundation for the Company through to the expected commencement of cash flow receipts from Ruvuma. We are thankful for the participation of all the investors, including our largest shareholder, Eclipse Investments LLC.

 

We expect 2023 to be a decisive year with significant information flow regarding multiple workstreams. The operator's capacity to run numerous critical negotiations and a significantly broader technical engagement, fully supported by the Tanzanian authorities, has significantly shortened the time to gas production, now targeted for October 2023. This development has shifted the narrative of Ruvuma, further de-risking the project from a dependence on the spudding and outcome of CH-1 to a more anchored and broader development effort as we move toward early gas production. Such de-risking continues to honour the upside potential that will come from the drilling of CH-1, the 3D seismic interpretation, and the full development of the field. These developments are potential game-changers for all stakeholders in the Ruvuma development.

 

Finally, I would like to thank our shareholders for their continued support and patience and hope that our operations in 2023 will ultimately reward us all with success on Ntorya.

 

Yours sincerely,

 

Charles Santos

Executive Chairman

Friday, 2 December 2022

Aminex 30KM Gas Pipeline Construction

 As in the most recent RNS, the Tanzanian Minister of Energy and Managing Director of TPDC outlined the Government's strong commitment to:

· Develop additional gas resources as soon as possible;

· Accelerate Ruvuma's production, which will play a vital role in achieving the country's short to medium-term gas needs; and

· Construct a 30 km pipeline to tie the Ntorya gas field into the existing Madimba processing and pumping station in the next six to nine months.

Monday, 21 February 2022

Action on the Ground - Signs of Aminex 3D Seismic Survey

 Aminex Seismic Action


There are signs of action from Aminex ARA on the ground with discernible tracks showing across the proposed seismic survey area

Stock Image

Monday, 31 January 2022

Anticipation of An Aminex Update

What is that Aminex update and when is it due?



The short answer, how long is a piece of string?

However, anticipation has been clearly building over recent weeks as the share has at time of writing almost doubled in value to a level that in my view is still massively undervalued at this stage!

Sunday, 25 October 2020

Aminex to feed Madimba Gas Plant

Aminex Ruvuma Development
(As known contained within the Farm-out circular dated 7th December 2018)
Forming part of the binding agreement between APT and the company



5.7 Development Cost Estimates

The initial production scheme, Case A, is designed to produce from three wells with flowlines tied to a central manifold. Onward transmission to the Madimba plant is via a 18” line. This is expected to be supplemented by a further eight wells, Case B, to absorb the remaining plant ullage. Flow assurance has been assessed with no significant issues foreseen.

Friday, 23 October 2020

Aminex PLC RNS Announcement - Farm-out completion

Aminex Farm out Completion



23 October 2020

AMINEX PLC (“Aminex” or “the Company”)

Completion of Ruvuma Farm-Out Aminex is pleased to announce the Completion of the Ruvuma Farm-Out. The Company, through its wholly owned subsidiary, Ndovu Resources Limited, has transferred a 50% interest in, and operatorship of, the Ruvuma PSA to ARA Petroleum Tanzania Limited (“APT”).

Wednesday, 21 October 2020

An Aminex Message From Drewky

A Message from Drewky

A reassurance for those on the bulletin boards in the last few days who are either ignorant or willingly ignoring the fact that the companies have a binding agreement.

With the Tanzanian agreement to the farm-out already notified the confirmation that is awaited for at this time can simply be the transference of operatorship to APT as per terms of that binding agreement.

As is well known by genuine investors the circular mentioned in the following RNS was duly circulated and voted through positively by the shareholders. Anyone voting on this matter should have no excuses for not knowing it's full contents.

The delays we have had in obtaining this clearance for almost two years have clearly been in country as everyone knows. We are now set to reap the rewards


11 July 2018

AMINEX PLC

(“Aminex” or “the Company”)

Transformational Ruvuma Farm-Out

Aminex is pleased to announce that its wholly-owned subsidiary, Ndovu Resources Limited, has signed a binding farm-out agreement (“Farm-Out”) with The Zubair Corporation LLC (“Zubair”). Zubair plans to assign its interest in the Farm-Out to ARA Petroleum Tanzania Ltd (a company under formation) (“APT”), which will be an affiliate of Eclipse Investments LLC (“Eclipse”), the Company’s largest shareholder.

Monday, 12 October 2020

Aminex PLC - Drewky's List

Congratulations to each and everyone of you, it's been a long time coming but hopefully you will all feel a little better tonight.  It was never in doubt for me although I admit my bottom was begining to twitch over the last few days.

Anyway Good luck to you all. Raise a glass and one day soon we may just well have that party! Here is the updated list and if it helps people to understand where we are then please share.

Tuesday, 25 February 2020

Things are moving at last for Aminex RNS - Corporate & Operations Update

I feel the following RNS is a fairly positive one and although things are still awaiting governmental approvals, I highlight the things I have picked out and make [comment] accordingly 
25th February 2020  

Aminex plc 

("Aminex" or "the Company")    

Corporate and Operations Update

Aminex announces the following update regarding the Company's ongoing operations in Tanzania and other corporate matters.

Highlights:

·    APT and Aminex have agreed that upon completion of the Farm-Out and the transfer of operatorship to APT, they will seek permission from the Joint Venture and the Tanzanian authorities to move the contingent elements of the 2020 work programme into the firm budget

·    Positive indications in-country that, after a period of reduced corporate engagement, the Government is re-engaging with the international business community to support the country's power demands

Monday, 10 December 2018

Aminex announcement on remedial programme success at Kiliwani North

Aminex announces completion of remedial programme at Kiliwani North

Aminex plc (LON:AEX) has confirmed the successful completion of remedial work for the Kiliwani North-1 production well in Tanzania.